bologna_5_s06 208

32

 
 
 
 
 
 
 

Recent   Works   and     Past Performance

From the date RAMIN AVIATION was founded and till now the company keeps doing its job by executing and implementing different ATM projects. The list below comprises some of the Company's projects.
 

A. Recent Work:

1.      The Civil Aviation State Establishment:

a.        Three systems have been installed at Hashmiya, Shatra, Baserah and are all operational.

b.      The forth has been installed at Alqosh in 20 may 2008 and has become operational.

c.       The civil works at Samarra and Hawiga are under construction for installation of the next two VORs.

d.      Preparations are taking place to install other two stations in Kut and Najaf.

 2.      Sulaimaniya  International airport:

a.       Maintenance of the previously installed equipment by the AGS company with calibration and has been set operational.

b.      Installation of a new ILS system including the civil and electrical works. This systems included the equipment:

                           i.      LLZ 422 complete.

                         ii.      GP 421.

                        iii.      DME 415.

                       iv.      RCSU 433.

 

3.      Erbil International airport:

a.       Supply and installation of a new DME 435 – power 1000W in conjunction with the existing DVOR.

b.      Maintenance operating of other old equipment and returning them operational.

 

4.      Basra International airport:

a.       Installation of ILS system (American MK20A) in cooperation with the American Thales.

b.      Installation of a new CVOR and DME.

 

 

B. Agreements
2005: A Memorandum of Agreement has been signed between Ramin Aviation and ASI, whereas, ASI is working to certify Ramin Aviation to install, and to be trained and certified for on-going maintenance of ground based electronic navigational equipment for Iraq. ASI and Ramin Aviation Co. will work together to identify potential business opportunities relating to infrastructure and communications systems in Iraq.

C. Signed Contracts
 2005: A contract signed between Ramin Aviation Company and THALES Company regarding supply, installation, setting up , commissioning and ground test of 9 CVOR navigation systems for the benefit of the Iraqi Civil Aviation Authority. Installation will be performed along the civil aviation en-route paths throughout Iraq.

Hereafter, are stated the places and dates of installation, setup and commissioning of the equipment.

 
D. Studies and surveys
2005: A comprehensive thorough study to develop Sulaymaniya Airport and the assessment of its main elements in providing the highest level of safety for the aircrafts and the passenger streamlines and comfort ability were encompassed.

E. Airport Constructions
Participating in engineering planning, supervising and carrying on several constructional tasks in the following airports – both civil and military:
oMUTHANA AP
oBASRAH IAP
oMOUSOL AP
oQadisiya Air Base
oBALAD Air Base


F. NavAids installations
2001: Install a new (VOR+DME) station in MANDELY.
2000: Install a new (VOR+DME) station in HADITHA and BASRAH IAP.
2000: Transfer 2 sets of ILS from (BIAP) to BASRAH IAP runway
1996: Transfer (VOR + DME) station at SAMARA.
1994: Transfer a (DVOR + DME) station from the side 33R to 15R of BIAP.
1990: Install (VOR + DME) station in ABUGRAYB (AD) near BIAP.
1987: Transfer of three VOR + DME station which was SHARGAT (SH), HADIHA (HD), SAMARA (SM) to HAWIJA , ZUBAYDIA, SAMARA.

G. Radar installations
2003: Installation of ATCR-33 system at AL-RASHEED Air Base / BAGHDAD.
1994: Installation of ATCR-33 system at SIWAYRA Air Base / BAGHDAD
1989: Installation of ATCR-33 system at MOUSOL Air Base / Mosul Governorate.
1989: Installation of ATCR-33 system at BIAP.
1988: Installation of ATCR-33 system at SAAD Air Base / AL-ANBAR Governorate.
1987: Installation of ATCR-33 system at Qadisya Air Base / AL-ANBAR Governorate.
1987: Installation of ATCR-33 system at JELEBAH Air Base / Nasirya Governorate.
1987: Installation of ATCR-33 system at SHEAIBAH Air Base / BASRA Governorate.
1986: Installation of ATCR-33 system at KUT Air Base / WASIT GOV.
1984: Installation of ATCR-33 system at AL-WALEED Air Base / AL-ANBAR Governorate.
1984: Installation of ATCR-33 system at ALI Air Base / Nasirya GOV.
1984: Installation of ATCR-33 system at QAYARA Air Base / Mosul Governorate.
1983: Installation of ATCR-33 system at HABANYAH Air Base / AL-ANBAR Governorate.
1983: Installation of ATCR-33 system at BALAD Air Base / BAGHDAD.
1983: Installation of ATCR-33 system at TIKRIT Air Base / SALAH EL-DIN Governorate.
1982: Installation of ATCR-33 system MUTHANA AP. / BAGHDAD.
1982: Installation of ATCR-33 system at AL-RASHEED Air Base / BAGHDAD.

G. AFL installations
•Installation of 13 fixed AFL systems (ADB type – Belgium and Philips – Netherlands) all over Iraqi Airbases and Airports.
•Installation of 20 portable AFL systems in Iraqi Airbases as temporary installations to promote rapid setup and operation for military operational purposes.
•Installation of 5 heliport lightings.

H. Other installations
Installations and commissioning of a variety of equipments throughout Iraqi airports, e.g.,
•Many HF, VHF and UHF communication equipment (Transmitter and Receiver stations with all their details and compact transceivers).
•Many ATIS, VOLMET equipment and intercoms.
•Performing Integration of all NAVAIDs, radios, RVR signals and other ATC and airfield systems at MUTHANA AP. ATC tower / BAGHDAD at 1992 to support full capacity airfield operations in the pertinent airport
•Fifteen Precision Approach Radars – PAR.
•Eighteen Directional Finders – DF equipment – Fixed and portable versions.
•Four VSAT Systems; one main station in Baghdad and three remote stations at Western, Southern and Northern sectors of Iraq

 

8
9
36